Data Entry in the Time-phase Pane
You can manually adjust the spread of the resources within the control account or work package dates in the Time-phase pane.
The total time-phased spread display at the control account or work package level if the Show Summary option in the Data group on the Edit tab is selected. The Total row displays the total time-phased spread at the project-level based on the filter applied to the project view.
You can spread resources within the dates of the respective control account or work package. When you enter or update data in the Time-phase pane, the Time-phase Detail pane is updated at the same time. The Time-phase pane is updated after you save your changes in the Time-phase Detail pane or navigate to another row in the Spreadsheet pane.
- Spread
- Reconcile
- Fix Spread